Apply for Site Plan Review
Site Plan Review – Flow Chart
(Commercial or Multi-Family Development)
Time |
Sketch Plan Submission
Submit Complete Sketch Plan Application
(Voluntary but Recommended)
|
2 Weeks |
Sketch Plan Review by Planning Board
(Voluntary but Recommended)
|
3 to 6 Weeks |
Site Plan Submission
Planning Staff / Engineering Review
|
Site Plan Review by Planning Board
(Smaller projects with complete applications
and conforming designs can be approved in
one meeting by the Planning Board)
|
3 Weeks |
Site Plan Approval by Planning Board
(Larger or more complex applications take multiple Planning Board meetings and are dependent on applicant’s ability to update plans and conform to standards)
|
5 to 12 Weeks – General Town Review Period
(This does not include review time by State and Federal review agencies)
|
Click here to download the Town of Scarborough, Maine Site Plan Checklist