Site Plan Review – Flow Chart
(Commercial or Multi-Family Development)
| Time | Sketch Plan Submission Submit Complete Sketch Plan Application (Voluntary but Recommended) |
| 2 Weeks | Sketch Plan Review by Planning Board (Voluntary but Recommended) |
| 3 to 6 Weeks | Site Plan Submission Planning Staff / Engineering Review |
| Site Plan Review by Planning Board (Smaller projects with complete applications and conforming designs can be approved in one meeting by the Planning Board) | |
| 3 Weeks | Site Plan Approval by Planning Board (Larger or more complex applications take multiple Planning Board meetings and are dependent on applicant’s ability to update plans and conform to standards) |
| 5 to 12 Weeks – General Town Review Period (This does not include review time by State and Federal review agencies) | |